3RD WATER TREATMENT PLANT OF MASHHAD CITY

3RD WATER TREATMENT PLANT OF MASHHAD CITY

 

3RD WATER TREATMENT PLANT OF MASHHAD CITY

 

• Client: khorasan regional water Authority
• Consultant: Sarv-Ab Consulting Engineers Co.
• Contract Date: 2004
Project specification

Our company is in charge of detail designing procurement ,construction ,commissioning and 6-month-operation.

The Project is still under construction and the plant would be operational on 2009 based on the project time schedule

·apacity: 6 m3/sec

·lant system: Super pullsator

Major activity and quantities

· Earthwork   450,000 m3

· Reinforcement   5,500 ton

· Formwork   110,000 m2

· Concrete   50,000 m3

· Steel structures  220 ton

· Design,procurement,installation of the plant facilities