Failed to load licensing components!

Please RE-INSTALL / REPAIR SKIN! DO NOT UNINSTALL THEME which will cause unrecoverable data loss!

News IEC

IEC has been designing and constructing pipeline installations for over thirty years in locations around the regions. 

3RD WATER TREATMENT PLANT OF MASHHAD CITY

3RD WATER TREATMENT PLANT OF MASHHAD CITY

 

3RD WATER TREATMENT PLANT OF MASHHAD CITY

 

• Client: khorasan regional water Authority
• Consultant: Sarv-Ab Consulting Engineers Co.
• Contract Date: 2004
Project specification

Our company is in charge of detail designing procurement ,construction ,commissioning and 6-month-operation.

The Project is still under construction and the plant would be operational on 2009 based on the project time schedule

·apacity: 6 m3/sec

·lant system: Super pullsator

Major activity and quantities

· Earthwork   450,000 m3

· Reinforcement   5,500 ton

· Formwork   110,000 m2

· Concrete   50,000 m3

· Steel structures  220 ton

· Design,procurement,installation of the plant facilities

Related

Tags

Categories

Share

Post a Comment